Pajuperankagas Wind Farm is an 86.8MW onshore wind power project. It is planned in Northern Ostrobothnia, Finland. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the under construction stage. It will be developed in a single phase. The project construction is likely to commence in 2022 and is expected to enter into commercial operation in November 2023. Buy the profile here.

Description

The project is being developed by ABO Wind and Infinergies Finland. The project is currently owned by ABO Wind with a stake of 100%.

The project cost is expected to be around $163.01m.

The project will have 169m high towers.

Development status

The project construction is expected to commence from 2022. Subsequent to that it will enter into commercial operation by November 2023.

Power purchase agreement

The power generated from the project will be sold to Statkraft under a power purchase agreement for a period of 10 years.

Contractors involved

ABO Wind is expected to render engineering procurement construction services for the wind power project.

Vestas Wind Systems will be the turbine supplier for the wind power project. The company is expected to provide 14 units of V162-6.2 turbines, each with 6.2MW nameplate capacity.

Vestas Wind Systems is expected to perform operations and maintenance for the wind power project for a period of 25 years.

For more details on Pajuperankagas Wind Farm, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.