Pesur – Repotenciado is a 42MW onshore wind power project. It is located in Andalusia, Spain. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 2008. Buy the profile here.
Description
The project is developed and owned by Sociedad Eolica de Andalucia.
The project generates 130,872MWh electricity thereby offsetting 51,040t of carbon dioxide emissions (CO2) a year. The project cost is $89.04m.
Development status
The project is currently active. The project got commissioned in 2008.
Contractors involved
Enercon was selected as the turbine supplier for the wind power project. The company provided 21 units of E-70 turbines, each with 2MW nameplate capacity.