Petropavlovsk CHP-2 Plant is a 541MW coal fired power project. It is located in North Kazakhstan, Kazakhstan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in December 1961. Buy the profile here.

Description

The project is currently owned by Sevkazenergo with a stake of 100%.

It is a Steam Turbine with Cogen power plant. The fuel is procured from Ekibastuz basin.

The project generated 3,226,200MWh of electricity.

Development status

The project got commissioned in December 1961.

Contractors involved

The Coal fired project have been supplied by Power Machines and Ural Turbine Works.

The electric generators for the project were procured from NPO Elsib and Ural Turbine Works.

For more details on Petropavlovsk CHP-2 Plant, buy the profile here.