Piva is a 342MW hydro power project. It is located on Piva river/basin in Pluzine, Montenegro. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 1976. Buy the profile here.
Description
The project is currently owned by Elektroprivreda Crne Gore AD Niksic.
Piva is a reservoir based project. The hydro reservoir capacity is 880 million cubic meter. The gross head and net head of the project are 160m and 99.99m respectively. Piva (Piva A1 ) underwent through rehabilitation & modernization during 2018-2019.Piva (Piva A2) underwent through rehabilitation & modernization during April 2019-2020.Piva (Piva A3) underwent through rehabilitation & modernization during 2020-2021. The project generated 860 GWh of electricity.
Development status
The project got commissioned in 1976.
Contractors involved
Litostroj Power was selected as the turbine supplier for the hydro power project. The project consists of 3 units of Francis turbines, each with 114MW nameplate capacity.
Koncar Generators and Motors supplied 1 electric generator for the Piva (Piva A1 ). The generator capacity is 120 MVA.
Koncar Generators and Motors supplied 1 electric generator for the Piva (Piva A2). The generator capacity is 120 MVA.
Koncar Generators and Motors supplied 1 electric generator for the Piva (Piva A3). The generator capacity is 120 MVA.
For more details on Piva, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.