Pocerady Combined Cycle Power Plant is an 838MW gas fired power project. It is located in Vysocina, Czech Republic. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in March 2014. Buy the profile here.

Description

The project is currently owned by CEZ.

It is a Combined Cycle Gas Turbine (CCGT) power plant.

The project cost is $1,318.174m.

Development status

The project got commissioned in March 2014.

Contractors involved

Skoda Praha was selected to render engineering procurement construction services for the gas fired power project.

The Gas fired project have been supplied by Doosan Skoda Power and Siemens.

Doosan Skoda Power supplied electric generator for the project.

Doosan Skoda Power supplied electric generator for the project.

Doosan Skoda Power supplied electric generator for the project.

SES Tlmace supplied steam boiler for the project.

SES Tlmace supplied steam boiler for the project.

SES Tlmace supplied steam boiler for the project.

For more details on Pocerady Combined Cycle Power Plant, buy the profile here.