Pyeongtaek Thermal Power Plant is a 1,400MW gas fired power project. It is located in Gyeonggi, South Korea. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. The project construction commenced in 1977 and subsequently entered into commercial operation in April 1980. Buy the profile here.
Description
The project is currently owned by Korea Western Power with a stake of 100%.
It is a Steam Turbine power plant that is used for Middle load.
Development status
The project construction commenced in 1977 and subsequently entered into commercial operation in April 1980.
Contractors involved
Hyundai Engineering was selected to render engineering procurement construction services for the gas fired power project.
Pyeongtaek Thermal Power Plant (Pyeongtaek Thermal Power Plant Unit I) is equipped with Mitsubishi Power steam turbine. The phase consists of 1 steam turbine with 350MW nameplate capacity.
Pyeongtaek Thermal Power Plant (Pyeongtaek Thermal Power Plant Unit II) is equipped with Mitsubishi Power steam turbine. The phase consists of 1 steam turbine with 350MW nameplate capacity.
Pyeongtaek Thermal Power Plant (Pyeongtaek Thermal Power Plant Unit III) is equipped with Mitsubishi Power steam turbine. The phase consists of 1 steam turbine with 350MW nameplate capacity.
Pyeongtaek Thermal Power Plant (Pyeongtaek Thermal Power Plant Unit IV) is equipped with Mitsubishi Power steam turbine. The phase consists of 1 steam turbine with 350MW nameplate capacity.
Mitsubishi Power supplied electric generator for the Pyeongtaek Thermal Power Plant (Pyeongtaek Thermal Power Plant Unit I).
Mitsubishi Power supplied electric generator for the Pyeongtaek Thermal Power Plant (Pyeongtaek Thermal Power Plant Unit II).
Mitsubishi Power supplied electric generator for the Pyeongtaek Thermal Power Plant (Pyeongtaek Thermal Power Plant Unit III).
Mitsubishi Power supplied electric generator for the Pyeongtaek Thermal Power Plant (Pyeongtaek Thermal Power Plant Unit IV).
Babcock & Wilcox Enterprises supplied steam boiler for the Pyeongtaek Thermal Power Plant (Pyeongtaek Thermal Power Plant Unit I).
Mitsubishi Power supplied steam boiler for the Pyeongtaek Thermal Power Plant (Pyeongtaek Thermal Power Plant Unit II).
Mitsubishi Power supplied steam boiler for the Pyeongtaek Thermal Power Plant (Pyeongtaek Thermal Power Plant Unit III).
Mitsubishi Power supplied steam boiler for the Pyeongtaek Thermal Power Plant (Pyeongtaek Thermal Power Plant Unit IV).
For more details on Pyeongtaek Thermal Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.