Pyhakoski is a 149MW hydro power project. It is located on Oulu river/basin in Northern Ostrobothnia, Finland. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1945 and subsequently entered into commercial operation in 1949. Buy the profile here.
Description
The project is currently owned by Fortum with a stake of 100%.
The gross head of the project is 32.4m. Pyhakoski underwent through rehabilitation & modernization during 2013. The project generated 555 GWh of electricity.
Development status
The project construction commenced in 1945 and subsequently entered into commercial operation in 1949.
Contractors involved
The turbines for the hydro power project have been supplied by Litostroj Power and Oy Tampella.
GE Renewable Energy supplied 1 electric generator for the project.
GE Renewable Energy supplied 2 electric generators for the project. The generator capacity is 40 MVA.
GE Renewable Energy supplied 1 electric generator for the project. The generator capacity is 45 MVA.
Caverion is the O&M contractor for the hydro power project.