The Remy Jade Gas Power Plant is 288MW gas fired power project. It is planned in Texas, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the financed stage. It will be developed in a single phase. Post completion of the construction, the project is expected to get commissioned in January 2024. Buy the profile here.
Description
The project is currently owned by WattBridge Energy with a stake of 100%.
It is a Thermal power plant. The fuel will be procured from Kinder Morgan Tejas Pipeline LLC.
The project cost is expected to be around $399.514m.
Development status
Post completion of the construction, the project is expected to get commissioned in January 2024.
Contractors involved
ProEnergy Services is expected to render engineering procurement construction services for the gas fired power project.
GE Power will be the turbine supplier for the Gas fired project. The company is expected to provide 6 units of LM6000PC gas turbines.
ProEnergy Services is expected to perform operations and maintenance for thermal power project.
For more details on Remy Jade Gas Power Plant, buy the profile here.