Rio Bravo II (Anahuac) Combined Cycle Power Plant is a 544MW gas fired power project. It is located in Tamaulipas, Mexico. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in January 2002. Buy the profile here.
Description
The project was developed by EDF International and MT Falcon Holdings Company S.A.P.I. de. The project is currently owned by Actis with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Gasoducto del Rio SA de CV.
The project generated 3,556,000MWh of electricity.
Development status
The project got commissioned in January 2002.
Power purchase agreement
The power generated from the project is sold to Comision Federal de Electricidad under a power purchase agreement for a period of 25 years.
Contractors involved
The Gas fired project have been supplied by GE Power and Siemens Energy.
The electric generators for the project were procured from GE Power and Siemens Energy.
John Cockerill Group supplied steam boiler for the project.
John Cockerill Group supplied steam boiler for the project.
John Cockerill Group supplied steam boiler for the project.
Compania Mexicana de Gerencia y Operaciones is the O&M contractor for thermal power project.
For more details on Rio Bravo II (Anahuac) Combined Cycle Power Plant, buy the profile here.
About MT Falcon Holdings Company S.A.P.I. de
MT Falcon Holdings Co SAPI de CV operates as a holding company. It falls under the management of companies and enterprises umbrella. The company is headquartered in Mexico City, Mexico.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.