Romero Solar PV Park is an 11MW solar PV power project. It is planned in Maule, Chile. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the under construction stage. It will be developed in a single phase. The project construction is likely to commence in 2021 and is expected to enter into commercial operation in 2023. Buy the profile here.

Description

The project is being developed by Parque Solar El Sauce and is currently owned by PV Power with a stake of 100%.

Romero Solar PV Park is a ground-mounted solar project which is planned over 17.3 hectares.

The project cost is expected to be around $9m.

The solar power project consists of 28,080 modules, each with 380W nameplate capacity.

Development status

The project construction is expected to commence from 2021. Subsequent to that it will enter into commercial operation by 2023.

For more details on Romero Solar PV Park, buy the profile here.

About Parque Solar El Sauce

Parque Solar El Sauce SpA (Parque Solar El Sauce) focuses on operation of a photovoltaic module plant for the generation of electrical energy. The company is located in Chile.