Ryazanskaya GRES Phase II is a 1,600MW gas fired power project. It is located in Ryazan, Russia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 1980. Buy the profile here.
Description
The project is currently owned by OGK-2 with a stake of 100%.
It is a Steam Turbine with Cogen power plant that is used for Baseload. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Fuel Oil.
Development status
The project got commissioned in December 1980.
Contractors involved
Leningradsky Metallichesky Zavod was selected as the turbine supplier for thermal power project. The project consists of 2 units of K-800-240 turbines, each with 800MW nameplate capacity.
Electrosila supplied TZV-800-2UZ electric generator for the Ryazanskaya GRES Phase II (Ryazanskaya GRES Phase II Unit I).
Electrosila supplied TZV-800-2UZ electric generator for the Ryazanskaya GRES Phase II (Ryazanskaya GRES Phase II Unit II).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Ryazanskaya GRES Phase II (Ryazanskaya GRES Phase II Unit I).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Ryazanskaya GRES Phase II (Ryazanskaya GRES Phase II Unit II).
For more details on Ryazanskaya GRES Phase II, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.