Sagae is a 75MW hydro power project. It is located on Sagae river/basin in Yamagata, Japan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1972 and subsequently entered into commercial operation in 1990. Buy the profile here.

Description

The project is currently owned by Tohoku Electric Power.

The hydro reservoir capacity is 109 million cubic meter. The net head of the project is 117.75m. The project generated 242.854 GWh of electricity.

The hydro power project consists of 1 turbine with 77MW nameplate capacity.

The project has 1 electric generator installed at the site. The generator capacity is 83.4 MVA.

Development status

The project construction commenced in 1972 and subsequently entered into commercial operation in 1990.

For more details on Sagae, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.