Sengkang Combined Cycle Power Plant is a 315MW gas fired power project. It is located in South Sulawesi, Indonesia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in September 1997. Buy the profile here.
Description
The project is currently owned by PT Energi Sengkang.
It is a Combined Cycle Gas Turbine (CCGT) power plant that is used for Baseload. The fuel is procured from Kampung Baru Gas Field.
Development status
The project got commissioned in September 1997.
Power purchase agreement
The power generated from the project is sold to PT PLN (Persero) under a power purchase agreement for a period of 25 years. The contracted capacity is 315MW.
Contractors involved
ABB Kraftwerke was selected to render engineering procurement construction services for the gas fired power project.
Sengkang Combined Cycle Power Plant (Sengkang Combined Cycle Power Plant Block I Unit I) is equipped with GE Power GT8C gas turbine. The phase consists of 1 gas turbine with 85MW nameplate capacity.
Sengkang Combined Cycle Power Plant (Sengkang Combined Cycle Power Plant Block I Unit II) is equipped with GE Power steam turbine. The phase consists of 1 steam turbine with 50MW nameplate capacity.
Sengkang Combined Cycle Power Plant (Sengkang Combined Cycle Power Plant Block II Unit I) is equipped with Siemens gas turbine. The phase consists of 1 gas turbine with 60MW nameplate capacity.
Sengkang Combined Cycle Power Plant (Sengkang Combined Cycle Power Plant Block II Unit II) is equipped with Siemens GT22 gas turbine. The phase consists of 1 gas turbine with 60MW nameplate capacity.
Sengkang Combined Cycle Power Plant (Sengkang Combined Cycle Power Plant Block II Unit III) is equipped with GE Power ST28 steam turbine. The phase consists of 1 steam turbine with 60MW nameplate capacity.
GE Power supplied electric generator for the Sengkang Combined Cycle Power Plant (Sengkang Combined Cycle Power Plant Block I Unit I).
GE Power supplied electric generator for the Sengkang Combined Cycle Power Plant (Sengkang Combined Cycle Power Plant Block I Unit II).
Siemens supplied electric generator for the Sengkang Combined Cycle Power Plant (Sengkang Combined Cycle Power Plant Block II Unit I).
Siemens supplied electric generator for the Sengkang Combined Cycle Power Plant (Sengkang Combined Cycle Power Plant Block II Unit II).
GE Power supplied TOPACK electric generator for the Sengkang Combined Cycle Power Plant (Sengkang Combined Cycle Power Plant Block II Unit III).
GE Power supplied steam boiler for the Sengkang Combined Cycle Power Plant (Sengkang Combined Cycle Power Plant Block I Unit I).
GE Power supplied steam boiler for the Sengkang Combined Cycle Power Plant (Sengkang Combined Cycle Power Plant Block II Unit I).
GE Power supplied steam boiler for the Sengkang Combined Cycle Power Plant (Sengkang Combined Cycle Power Plant Block II Unit II).
For more details on Sengkang Combined Cycle Power Plant, buy the profile here.