Seraing Combined Cycle Power Plant is a 470MW gas fired power project. It is located in Liege, Belgium. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1994 and subsequently entered into commercial operation in August 1994. Buy the profile here.

Description

The project is currently owned by Electricite de France with a stake of 68.63%.

It is a Combined Cycle Gas Turbine (CCGT) power plant that is used for Reserve.

Development status

The project construction commenced in 1994 and subsequently entered into commercial operation in August 1994.

Contractors involved

The Gas fired project have been supplied by GE Power and Siemens.

The electric generators for the project were procured from GE Power and Siemens.

John Cockerill Group supplied steam boiler for the project.

John Cockerill Group supplied steam boiler for the project.

John Cockerill Group supplied steam boiler for the project.

For more details on Seraing Combined Cycle Power Plant, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.