Shamkir is a 380MW hydro power project. It is located on Kura river/basin in Ganja-Gazakh, Azerbaijan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 1982. Buy the profile here.

Description

The project is currently owned by AzerEnerji.

The hydro reservoir capacity is 1,420 million cubic meter. The net head of the project is 47.5m. The project generated 772 GWh of electricity.

Development status

The project got commissioned in 1982.

Contractors involved

Ukrainian Energy Machines was selected as the turbine supplier for the hydro power project. The company provided 2 units of kaplan turbines, each with 195MW nameplate capacity.

NPO Elsib supplied 2 electric generators for the project. The generator capacity is 224 MVA.

For more details on Shamkir, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.