Songas Ubungo Gas Turbine Power Plant is a 192MW gas fired power project. It is located in Dar es Salaam, Tanzania. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in August 2004. Buy the profile here.
Description
The project was developed by Songas. Globeleq Africa, Tanzania Petroleum Development and Tanzania Electric Supply are currently owning the project having ownership stake of 54.1%, 28.69% and 9.56% respectively.
It is a Gas Turbine power plant that is used for Baseload. The fuel is procured from Songo Songo Gas Field.
Development status
The project got commissioned in August 2004.
Power purchase agreement
The power generated from the project is sold to Tanzania Electric Supply under a power purchase agreement. The power is sold at the rate of $0.06kWh for a period of 20 years. The contracted capacity is 178.114MW.
Contractors involved
The Gas fired project have been supplied by GE Power and Siemens.
GE Power supplied electric generator for the project.
GE Power supplied electric generator for the project.
GE Power supplied electric generator for the project.
GE Power is the O&M contractor for thermal power project for a period of 8 years.
For more details on Songas Ubungo Gas Turbine Power Plant, buy the profile here.
About Songas
Songas Limited (Songas), a subsidiary of Globeleq Generation Limited, is an energy company that generates and supplies electricity; and processes and supplies gas. The company generates power from its gas-fired Ubungo power plant.