Soro is a 160MW hydro power project. It is planned on Molloco & Palca river/basin in Arequipa, Peru. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the under construction stage. It will be developed in a single phase. Post completion of the construction, the project is expected to get commissioned in 2026. Buy the profile here.
Description
The project is being developed by Generadora Electrica Molloco SAC. Enex O&M de Sistemas Eletricos, Engevix Engenharia e Projetos and Grupo Isolux Corsan are currently owning the project.
Soro is a reservoir based project. The gross head and net head of the project will be 1,246.2m and 1,218.5m respectively.
The hydro power project consists of 2 turbines, each with 83.1MW nameplate capacity.
The project will have 2 electric generators installed at the project site. The generator capacity is likely to be 95.76 MVA.
Development status
Post completion of the construction, the project is expected to get commissioned in 2026.
For more details on Soro, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.