Srepok 4 is an 80MW hydro power project. It is located on Srepok river/basin in Dac Lak, Vietnam. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2008 and subsequently entered into commercial operation in 2010. Buy the profile here.
Description
The gross head of the project is 21.4m. The project generated 336.36 GWh of electricity.
Development status
The project construction commenced in 2008 and subsequently entered into commercial operation in 2010.
Power purchase agreement
The power generated from the project is sold to Vietnam Electricity under a power purchase agreement.
Contractors involved
Dongfang Electric was selected as the turbine supplier for the hydro power project. The company provided 2 units of kaplan turbines, each with 41.2MW nameplate capacity.
Dongfang Electric supplied 2 electric generators for the project. The generator capacity is 47 MVA.
For more details on Srepok 4, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.