Stewartville is an 182MW hydro power project. It is located on Madawaska river/basin in Ontario, Canada. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 1948. Buy the profile here.

Description

The project was developed by Hydro-Electric Power Commission of Ontario and is currently owned by Ontario Power Generation with a stake of 100%.

Stewartville is a run-of-river project.

Development status

The project got commissioned in 1948.

Contractors involved

Allis-Chalmers Canada was selected as the turbine supplier for the hydro power project. The company provided 3 units of francis turbines, each with 20MW nameplate capacity.

Allis-Chalmers Canada was selected as the turbine supplier for the hydro power project. The company provided 2 units of francis turbines, each with 61MW nameplate capacity.

Canadian General Electric supplied electric generator(s) for the project.

For more details on Stewartville, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.