The Tangedco CCGT Power Plant-II is 730MW gas fired power project. It is planned in Tamil Nadu, India. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in a single phase. The project construction is likely to commence in 2025 and is expected to enter into commercial operation in 2026. Buy the profile here.

Description

The project is being developed and currently owned by Tamil Nadu Generation and Distribution. The company has a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel will be procured from Indian Oil Corporatio Limited, Ennore.

The project cost is expected to be around $487.859m.

Development status

The project construction is expected to commence from 2025. Subsequent to that it will enter into commercial operation by 2026.

For more details on Tangedco CCGT Power Plant-II, buy the profile here.

About Tamil Nadu Generation and Distribution

Tamilnadu Generation and Distribution Corporation Limited (TANGEDCO) is a subsidiary of TNEB( Tamilnadu Electricity Board) Limited that generates and distributes the electrical power. It provides services for the electric needs of the Tamilnadu state through four large thermal power stations. The corporation has two divisions one is Electricity generation wing and other is Electricity distribution wing. Its portfolio involves in generation of electricity through wind turbines. TANGEDCO is headquartered in Chennai, Tamil Nadu, India.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.