Tanjung Jati B Power Plant is a 4,640MW coal fired power project. It is located in Central Java, Indonesia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in October 2006. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Premium Insights Tanjung Jati B Power Plant

Buy the Profile

Premium Insights

The gold standard of business intelligence.

Find out more

Description

The project was developed by PT Bhumi Jati Power and PT Central Java Power. PT Central Java Power, PT United Tractors, Sumitomo and The Kansai Electric Power are currently owning the project.

It is a Steam Turbine power plant.

Development status

The project got commissioned in October 2006.

Power purchase agreement

The power generated from the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit I) is sold to PT PLN (Persero) under a power purchase agreement, starting from 2006.

The power generated from the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit II) is sold to PT PLN (Persero) under a power purchase agreement, starting from 2006.

The power generated from the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit III) is sold to PT PLN (Persero) under a power purchase agreement.

The power generated from the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit IV) is sold to PT PLN (Persero) under a power purchase agreement.

The power generated from the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase II Unit I (Unit V)) is sold to PT PLN (Persero) under a power purchase agreement for a period of 25 years.

The power generated from the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase II Unit II (Unit VI)) is sold to PT PLN (Persero) under a power purchase agreement for a period of 25 years.

Contractors involved

Sumitomo was selected to render engineering procurement construction services for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit I) project. Sumitomo was selected to render engineering procurement construction services for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit II) project. Sumitomo was selected to render engineering procurement construction services for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit III) project. Sumitomo was selected to render engineering procurement construction services for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit IV) project. Sumitomo was selected to render engineering procurement construction services for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase II Unit I (Unit V)) project. Sumitomo was selected to render engineering procurement construction services for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase II Unit II (Unit VI)) project. Toshiba JSW Power Systems was selected to render engineering procurement construction services for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit I) project. Toshiba JSW Power Systems was selected to render engineering procurement construction services for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit II) project. Toshiba JSW Power Systems was selected to render engineering procurement construction services for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit III) project. Toshiba JSW Power Systems was selected to render engineering procurement construction services for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit IV) project. Wasa Mitra Engineering was selected to render engineering procurement construction services for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase II Unit I (Unit V)) project. Wasa Mitra Engineering was selected to render engineering procurement construction services for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase II Unit II (Unit VI)) project.

Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit I) is equipped with Toshiba Energy Systems and Solutions steam turbine. The phase consists of 1 steam turbine with 660MW nameplate capacity.

Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit II) is equipped with Toshiba Energy Systems and Solutions steam turbine. The phase consists of 1 steam turbine with 660MW nameplate capacity.

Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit III) is equipped with Toshiba Energy Systems and Solutions steam turbine. The phase consists of 1 steam turbine with 660MW nameplate capacity.

Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit IV) is equipped with Toshiba Energy Systems and Solutions steam turbine. The phase consists of 1 steam turbine with 660MW nameplate capacity.

Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase II Unit I (Unit V)) is equipped with Toshiba Energy Systems and Solutions steam turbine. The phase consists of 1 steam turbine with 1,000MW nameplate capacity.

Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase II Unit II (Unit VI)) is equipped with Toshiba Energy Systems and Solutions steam turbine. The phase consists of 1 steam turbine with 1,000MW nameplate capacity.

Toshiba Energy Systems and Solutions supplied electric generator for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit I).

Toshiba Energy Systems and Solutions supplied electric generator for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit II).

Toshiba Energy Systems and Solutions supplied electric generator for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit III).

Toshiba Energy Systems and Solutions supplied electric generator for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit IV).

Toshiba Energy Systems and Solutions supplied electric generator for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase II Unit I (Unit V)).

Toshiba Energy Systems and Solutions supplied electric generator for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase II Unit II (Unit VI)).

Babcock & Wilcox Enterprises supplied steam boiler for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit I).

Babcock & Wilcox Enterprises supplied steam boiler for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit II).

Mitsubishi Power supplied steam boiler for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit III).

Mitsubishi Power supplied steam boiler for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase I Unit IV).

Mitsubishi Power supplied steam boiler for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase II Unit I (Unit V)).

Mitsubishi Power supplied steam boiler for the Tanjung Jati B Power Plant (Tanjung Jati B Power Plant Phase II Unit II (Unit VI)).

Fortum Service, Korea Midland Power, PT Bhumi Jepara Service, PT Medco Energi Internasional, PT Pembangkitan Jawa-Bali, PT TJB Power Services, PT United Tractors, Sumitomo and The Kansai Electric Power were contracted to render operations & maintenance services for the project.

For more details on Tanjung Jati B Power Plant, buy the profile here.

This content was updated on 4 January 2024

Premium Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.