Teverola Combined Cycle Power Plant is a 400MW gas fired power project. It is located in Campania, Italy. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2004 and subsequently entered into commercial operation in December 2006. Buy the profile here.

Description

The project was developed by Societa Europa Tessile. Repower and Hera are currently owning the project having ownership stake of 61% and 39% respectively.

It is a CCGT with Cogen power plant.

The project cost is $80.45m.

Development status

The project construction commenced in 2004 and subsequently entered into commercial operation in December 2006.

Contractors involved

Amec Foster Wheeler Italiana was selected to render engineering procurement construction services for the gas fired power project.

GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of 9FA gas turbine.

GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of A15 steam turbine.

GE Power supplied electric generator for the project.

GE Power supplied electric generator for the project.

Amec Foster Wheeler supplied steam boiler for the project.

Amec Foster Wheeler supplied steam boiler for the project.

For more details on Teverola Combined Cycle Power Plant, buy the profile here.