Tokuyama Coal Fired Power Plant is a 300MW coal fired power project. It is located in Yamaguchi, Japan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2017 and subsequently entered into commercial operation in September 2022. Buy the profile here.

Description

The project was developed by Marubeni Thermal Power. Tokyo Century, Marubeni Thermal Power and Tokuyama are currently owning the project having ownership stake of 60%, 20% and 20% respectively.

It is a Steam Turbine power plant.

The project cost is $809.52m.

Development status

The project construction commenced in 2017 and subsequently entered into commercial operation in September 2022.

Power purchase agreement

The power generated from the project is sold to Marubeni Power Retail under a power purchase agreement.

For more details on Tokuyama Coal Fired Power Plant, buy the profile here.

About Marubeni Thermal Power

Marubeni Thermal Power Co Ltd (Marubeni Thermal Power) is an energy service provider that offers electricity generation and transmission services. The company is located in Japan.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.