The Tongre Phase III Power Plant is 2,000MW coal fired power project. It is planned in Shanxi, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in multiple phases. Post completion of the construction, the project is expected to get commissioned in May 2024. Buy the profile here.
Description
The project is being developed and currently owned by Jinneng Holding Shanxi Electric Power. The company has a stake of 100%.
It is a Steam Turbine with Cogen power plant.
The project cost is expected to be around $1,333.4m.
The Coal fired project consists of 2 steam turbines.
Development status
Post completion of the construction, the project is expected to get commissioned in May 2024.
For more details on Tongre Phase III Power Plant, buy the profile here.
About Jinneng Holding Shanxi Electric Power
Jinneng Holding Shanxi Electric Power Co Ltd (Jinneng) formerly Shanxi Zhangze Electric Power Co Ltd, operates in the production and distribution of electricity and heat. The company also involves in the development and sale of fuel, materials, electric power technologies and power materials. Jinneng’s main products include thermal power electricity, wind power electricity, photovoltaic power, heat and coal among others. The company also provides maintenance services and finance lease services. It operates in China. Jinneng is headquartered in Taiyuan, China.