Torpshammar is an 117MW hydro power project. It is located on Ljungan river/basin in Vasternorrland, Sweden. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 1943. Buy the profile here.

Description

The project is currently owned by Vattenfall with a stake of 100%.

The hydro reservoir capacity is 2.5 million cubic meter. The gross head of the project is 123m. The project generated 360 GWh of electricity.

The hydro power project consists of 2 turbines.

Development status

The project got commissioned in 1943.

Contractors involved

GE Renewable Energy supplied 1 electric generator for the project. The generator capacity is 67 MVA.

For more details on Torpshammar, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.