Tuanpo is an 80MW hydro power project. It is located on Mengjiang river/basin in Guizhou, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2005 and subsequently entered into commercial operation in 2008. Buy the profile here.

Description

The project is developed and owned by Guizhou Mengjiang River Basin Development.

Tuanpo is a run-of-river project. The project generated 222.5 GWh of electricity. The project cost is $83.934m.

Development status

The project construction commenced in 2005 and subsequently entered into commercial operation in 2008.

Power purchase agreement

The power generated from the project is sold to Central China Grid under a power purchase agreement.

Contractors involved

Kunming Electric Machine was selected as the turbine supplier for the hydro power project. The company provided 1 turbine with 16MW nameplate capacity.

Kunming Electric Machine was selected as the turbine supplier for the hydro power project. The company provided 2 turbines, each with 32MW nameplate capacity.

Kunming Electric Machine supplied 3 electric generators for the project.

For more details on Tuanpo, buy the profile here.

About Guizhou Mengjiang River Basin Development

Guizhou Mengjiang River Basin Development Co., Ltd., is a hydroelectric power generation company in China, which owns 80 MW Tuanpo Hydropower Project.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.