The Tuzla Coal Fired Power Plant Unit VII & VIII is 900MW coal fired power project. It is planned in Tuzla, Bosnia and Herzegovina. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the under construction stage. It will be developed in multiple phases. The project construction is likely to commence in 2020 and is expected to enter into commercial operation in 2023. Buy the profile here.

Description

It is a Steam Turbine with Cogen power plant. The fuel will be procured from Kreka Coal Mine.

The project will generate 2,756,000MWh of electricity.

Development status

The project construction is expected to commence from 2020. Subsequent to that it will enter into commercial operation by 2023.

Contractors involved

China Gezhouba Group and Guangdong Electric Power Design Institute are expected to render engineering procurement construction services for the Tuzla Coal Fired Power Plant Unit VII & VIII (Tuzla Coal Fired Power Plant Unit VII).

Tuzla Coal Fired Power Plant Unit VII & VIII (Tuzla Coal Fired Power Plant Unit VII) will be equipped with Siemens Energy Three casing, Single Steam Reheating steam turbines.

Siemens Energy is expected to be the supplier of electric generator for the Tuzla Coal Fired Power Plant Unit VII & VIII (Tuzla Coal Fired Power Plant Unit VII).

GE Power is likely to be the supplier of steam boiler for the Tuzla Coal Fired Power Plant Unit VII & VIII (Tuzla Coal Fired Power Plant Unit VII).

For more details on Tuzla Coal Fired Power Plant Unit VII & VIII, buy the profile here.

About

JP Elektroprivreda BiH d.d. Sarajevo (EPBiH) is an electric utility company. The company generates, distributes, supplies and trades electricity. In addition the company also produces thermal energy and steam processing using coal and hydro sources. EPBiH owns and operates Jablanica, Grabovica, Salakovac hydro plants on the Neretva River and various small hydro power plants; and Tuzla and Kakanj thermal power plants. It distributes electricity in Una-Sana, Herzegovina-Neretva, Sarajevo, Bosnian-Podrinje, Central Bosnia, Tuzla, Zenica-Doboj cantons. The company is owned by the Government of Bosnia and Herzegovina, Investiciona grupa d.d. Sarajevo and other shareholders. EPBiH is headquartered in Sarajevo, Federation of Bosnia and Herzegovina.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.