Tyrsky Offshore Wind Farm is a 1,400MW offshore wind power project. It is planned in Gulf of Bothnia, Ostrobothnia, Finland. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the announced stage. It will be developed in a single phase. The project construction is likely to commence in 2026 and is expected to enter into commercial operation in 2030. Buy the profile here.
Description
The project is being developed and currently owned by OX2. The company has a stake of 100%.
The project is expected to generate 6,000,000MWh of electricity. The project cost is expected to be around $4,492.6m.
The wind power project consists of 100 turbines.
Development status
The project construction is expected to commence from 2026. Subsequent to that it will enter into commercial operation by 2030.
For more details on Tyrsky Offshore Wind Farm, buy the profile here.
About OX2
OX2 AB (OX2), formerly OX2 Wind AB, a subsidiary of Peas Industries AB, is a Swedish renewable energy company that develops renewable energy plants. The company develops, builds, finances, and manages renewable energy plants. Galatea-galene, riberget, and klevberget are OX2 projects. The company is headquartered in Stockholm, Sweden