Uch Power Station is a 931.3MW gas fired power project. It is located in Balochistan, Pakistan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in October 2000. Buy the profile here.
Description
The project is currently owned by UCH Power (Private) with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on High Speed Diesel. The fuel is procured from Uch Gas Field.
The project generated 5,066,000MWh of electricity.
Development status
The project got commissioned in October 2000.
Power purchase agreement
The power generated from the Uch Power Station (Uch Power Station Phase II) is sold to National Transmission & Despatch under a power purchase agreement for a period of 25 years.
Contractors involved
Descon Engineering and Hyundai Engineering & Construction were selected to render engineering procurement construction services for the Uch Power Station (Uch Power Station Phase II).
GE Power was selected as the turbine supplier for thermal power project. The project consists of 7 turbines.
GE Power supplied electric generator for the Uch Power Station (Uch Power Station Phase I).
Hamon Deltak supplied steam boiler for the Uch Power Station (Uch Power Station Phase I).
Hamon Deltak supplied steam boiler for the Uch Power Station (Uch Power Station Phase II).
For more details on Uch Power Station, buy the profile here.