Upper Trishuli 3A is a 60MW hydro power project. It is located on Trishuli river/basin in Bagmati, Nepal. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2011 and subsequently entered into commercial operation in 2019. Buy the profile here.

Description

The project was developed by Trishuli Jal Vidhyut and is currently owned by Nepal Electricity Authority with a stake of 30%.

Upper Trishuli 3A is a run-of-river project. The gross head of the project is 144.5m. The project generated 489.76 GWh of electricity. The project cost is $125.775m.

The hydro power project consists of 2 turbines, each with 30MW nameplate capacity.

Development status

The project construction commenced in 2011 and subsequently entered into commercial operation in 2019.

Contractors involved

China Gezhouba Group was selected to render engineering procurement construction services for the hydro power project.

For more details on Upper Trishuli 3A, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.