Valentuna Wind Farm is a 100MW onshore wind power project. It is planned in La Rioja, Spain. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in a single phase. Post completion of the construction, the project is expected to get commissioned in 2024. Buy the profile here.
Description
The project is being developed by Planta Solar Opde 40 and is currently owned by OPDE Holding with a stake of 100%.
The project cost is expected to be around $70.06m.
The wind power project consists of 30 turbines.
The project will have 101.5m high towers.
Development status
Post completion of the construction, the project is expected to get commissioned in 2024.