The Vedanta Jharsuguda Captive Power Plant is 3,195MW coal fired power project. It is planned in Odisha, India. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the partially active stage. It will be developed in multiple phases. Post completion of the construction, the project is expected to get commissioned in July 2008. Buy the profile here.
Description
The project is being developed and currently owned by Vedanta. The company has a stake of 100%.
It is a Steam Turbine power plant.
Development status
Post completion of the construction, the project is expected to get commissioned in July 2008.
Contractors involved
SEPCOIII Electric Power Construction is expected to render engineering procurement construction services for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit I) project. SEPCOIII Electric Power Construction is expected to render engineering procurement construction services for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit II) project. SEPCOIII Electric Power Construction is expected to render engineering procurement construction services for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit III) project. SEPCOIII Electric Power Construction is expected to render engineering procurement construction services for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit IV) project. SEPCOIII Electric Power Construction is expected to render engineering procurement construction services for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit IX) project. SEPCOIII Electric Power Construction is expected to render engineering procurement construction services for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit V) project. SEPCOIII Electric Power Construction is expected to render engineering procurement construction services for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit VI) project. SEPCOIII Electric Power Construction is expected to render engineering procurement construction services for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit VII) project. SEPCOIII Electric Power Construction is expected to render engineering procurement construction services for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit VIII) project.
Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit I) will be equipped with Shanghai Electric Group steam turbine. The phase consists of 1 steam turbine with 135MW nameplate capacity.
Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit II) will be equipped with Shanghai Electric Group steam turbine. The phase consists of 1 steam turbine with 135MW nameplate capacity.
Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit III) will be equipped with Shanghai Electric Group steam turbine. The phase consists of 1 steam turbine with 135MW nameplate capacity.
Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit IV) will be equipped with Shanghai Electric Group steam turbine. The phase consists of 1 steam turbine with 135MW nameplate capacity.
Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit IX) will be equipped with Shanghai Electric Group steam turbine. The phase consists of 1 steam turbine with 135MW nameplate capacity.
Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit V) will be equipped with Shanghai Electric Group steam turbine. The phase consists of 1 steam turbine with 135MW nameplate capacity.
Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit VI) will be equipped with Shanghai Electric Group steam turbine. The phase consists of 1 steam turbine with 135MW nameplate capacity.
Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit VII) will be equipped with Shanghai Electric Group steam turbine. The phase consists of 1 steam turbine with 135MW nameplate capacity.
Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit VIII) will be equipped with Shanghai Electric Group steam turbine. The phase consists of 1 steam turbine with 135MW nameplate capacity.
Shanghai Electric Group is expected to be the supplier of electric generator for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit I).
Shanghai Electric Group is expected to be the supplier of electric generator for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit II).
Shanghai Electric Group is expected to be the supplier of electric generator for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit III).
Shanghai Electric Group is expected to be the supplier of electric generator for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit IV).
Shanghai Electric Group is expected to be the supplier of electric generator for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit V).
Shanghai Electric Group is expected to be the supplier of electric generator for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit VI).
Shanghai Electric Group is expected to be the supplier of electric generator for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit VII).
Shanghai Electric Group is expected to be the supplier of electric generator for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit VIII).
Shanghai Electric Group is likely to be the supplier of steam boiler for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit I).
Shanghai Electric Group is likely to be the supplier of steam boiler for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit II).
Shanghai Electric Group is likely to be the supplier of steam boiler for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit III).
Shanghai Electric Group is likely to be the supplier of steam boiler for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit IV).
Shanghai Electric Group is likely to be the supplier of steam boiler for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit IX).
Shanghai Electric Group is likely to be the supplier of steam boiler for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit V).
Shanghai Electric Group is likely to be the supplier of steam boiler for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit VI).
Shanghai Electric Group is likely to be the supplier of steam boiler for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit VII).
Shanghai Electric Group is likely to be the supplier of steam boiler for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit VIII).
KEPCO Plant Service & Engineering is expected to perform operations and maintenance for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit I). The operation and maintenance contract tenure will likely be commencing from 2016, for a period of 5 years.
KEPCO Plant Service & Engineering is expected to perform operations and maintenance for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit II). The operation and maintenance contract tenure will likely be commencing from 2016, for a period of 5 years.
KEPCO Plant Service & Engineering is expected to perform operations and maintenance for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit III). The operation and maintenance contract tenure will likely be commencing from 2016, for a period of 5 years.
KEPCO Plant Service & Engineering is expected to perform operations and maintenance for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit IV). The operation and maintenance contract tenure will likely be commencing from 2016, for a period of 5 years.
KEPCO Plant Service & Engineering is expected to perform operations and maintenance for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit IX). The operation and maintenance contract tenure will likely be commencing from 2016, for a period of 5 years.
KEPCO Plant Service & Engineering is expected to perform operations and maintenance for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit V). The operation and maintenance contract tenure will likely be commencing from 2016, for a period of 5 years.
KEPCO Plant Service & Engineering is expected to perform operations and maintenance for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit VI). The operation and maintenance contract tenure will likely be commencing from 2016, for a period of 5 years.
KEPCO Plant Service & Engineering is expected to perform operations and maintenance for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit VII). The operation and maintenance contract tenure will likely be commencing from 2016, for a period of 5 years.
KEPCO Plant Service & Engineering is expected to perform operations and maintenance for the Vedanta Jharsuguda Captive Power Plant (Vedanta Jharsuguda Captive Power Plant Unit VIII). The operation and maintenance contract tenure will likely be commencing from 2016, for a period of 5 years.
For more details on Vedanta Jharsuguda Captive Power Plant, buy the profile here.
About Vedanta
Vedanta Ltd (Vedanta) is a diversified natural resource company with integrated metal and mining operations. The company carries out the exploration, extraction, and processing of m inerals, and oil and gas. It carries out the production and sale of oil and gas, aluminium, copper, iron ore, and power. Vedanta's product portfolio includes metals such as zinc, lead, silver, iron ore, steel, copper, and aluminium. It also carries out the production of pig iron and metallurgical coke. Vedanta has strategic assets in India, South Africa, and Namibia . The company has operational presence in the US, Asia-Pacific, Europe, the Middle East, and Africa. Vedanta is headquartered in Mumbai, Maharashtra, India.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.