Vientos del Secano Wind Farm is a 50MW onshore wind power project. It is located in Buenos Aires, Argentina. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in November 2020. Buy the profile here.
Description
The project was developed by ABO Wind Energias Renovables, Envision Energy (Jiangsu) and Envision Energy (Netherland). Envision Energy (Netherland) and Envision Energy (Jiangsu) are currently owning the project having ownership stake of 75% and 25% respectively.
The project generates 217GWh electricity thereby offsetting 75,000t of carbon dioxide emissions (CO2) a year.
The project has 90m high towers.
Development status
The project is currently active. The project got commissioned in November 2020.
Power purchase agreement
The power generated from the project is sold to Cammesa under a power purchase agreement. The power is sold at the rate of $0.049kWh for a period of 20 years. The contracted capacity is 50MW.
Contractors involved
Ingener and Milicic were selected to render engineering procurement construction services for the wind power project.
Envision Energy was selected as the turbine supplier for the wind power project. The company provided 20 units of EN110/2.5 turbines, each with 2.5MW nameplate capacity.
For more details on Vientos del Secano Wind Farm, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.