Vuelta De Obligado Power Generation Facility is an 810MW gas fired power project. It is located in Santa Fe, Argentina. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in November 2014. Buy the profile here.
Description
The project was developed by Central Vuelta de Obligado. Central Puerto, Enel Americas and Others are currently owning the project having ownership stake of 56%, 25.4% and 18.6% respectively.
It is a Combined Cycle Gas Turbine (CCGT) power plant.
The project cost is $850m.
Development status
The project got commissioned in November 2014.
Contractors involved
Duro Felguera, Fainser and GE Power were selected to render engineering procurement construction services for the gas fired power project.
Vuelta De Obligado Power Generation Facility (Vuelta De Obligado Power Generation Facility Unit I) is equipped with GE Power 9FA gas turbines. The phase consists of 2 gas turbines with 270MW nameplate capacity.
Vuelta De Obligado Power Generation Facility (Vuelta De Obligado Power Generation Facility Unit II) is equipped with GE Power D11 steam turbine. The phase consists of 1 steam turbine with 270MW nameplate capacity.
GE Power supplied electric generator for the project.
GE Power supplied electric generator for the project.
GE Power supplied electric generator for the project.
Hangzhou Boiler Group supplied steam boiler for the project.
Hangzhou Boiler Group supplied steam boiler for the project.
Hangzhou Boiler Group supplied steam boiler for the project.