Xiaoshixia is a 137.5MW hydro power project. It is located on Kumalake river/basin in Xinjiang Uyghur Autonomous Region, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. The project construction commenced in 2009 and subsequently entered into commercial operation in 2012. Buy the profile here.
Description
Xiaoshixia is a reservoir based project. The hydro reservoir capacity is 69 million cubic meter. The net head of the project is 44.6m. The project generated 418 GWh of electricity. The project cost is $133.49m.
The hydro power project consists of 5 turbines each with 27.5 MW nameplate capacity.
The project consists of 5 generators.
Development status
The project construction commenced in 2009 and subsequently entered into commercial operation in 2012.
For more details on Xiaoshixia, buy the profile here.