The Yeoju CCGT Power Plant is 1,000MW gas fired power project. It is planned in Gyeonggi, South Korea. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the under construction stage. It will be developed in a single phase. Post completion of the construction, the project is expected to get commissioned in August 2023. Buy the profile here.

Description

The project is being developed and currently owned by Yeoju Energy Service. The company has a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant.

The project cost is expected to be around $717.082m.

Development status

Post completion of the construction, the project is expected to get commissioned in August 2023.

Contractors involved

SK Ecoplant is expected to render engineering procurement construction services for the gas fired power project.

Siemens Energy will be the turbine supplier for the Gas fired project. The company is expected to provide 2 units of SGT6-9000HL gas turbines, each with 333MW nameplate capacity.

Siemens Energy will be the turbine supplier for the Gas fired project. The company is expected to provide 1 unit of SST6-5000 HI-L steam turbine with 334MW nameplate capacity.

Siemens Energy is expected to be the supplier of SGen6-2000P electric generator for the project.

Siemens Energy is likely to be the supplier of steam boiler for the project.

For more details on Yeoju CCGT Power Plant, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.