Yiyang Power Plant is a 1,800MW coal fired power project. It is located in Hunan, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 2001. Buy the profile here.
Description
The project is currently owned by Hunan Yiyang Power.
It is a Steam Turbine power plant that is used for Baseload.
Development status
The project got commissioned in 2001.
Contractors involved
Hunan Electric Power Design Institute was selected to render engineering procurement construction services for the Yiyang Power Plant (Yiyang Power Plant Phase II).
Yiyang Power Plant (Yiyang Power Plant Phase I) is equipped with Harbin Turbine N300-16.7/537/537 type steam turbines. The phase consists of 2 steam turbines with 300MW nameplate capacity.
Yiyang Power Plant (Yiyang Power Plant Phase II) is equipped with Shanghai Steam Turbine N600-24 · 2/566/566 steam turbines. The phase consists of 2 steam turbines with 600MW nameplate capacity.
Harbin Electric Machinery supplied QFSN-300-2 electric generator for the Yiyang Power Plant (Yiyang Power Plant Phase I).
Shanghai Electrical Machinery Group supplied QFSN-600-2 electric generator for the Yiyang Power Plant (Yiyang Power Plant Phase II).
Harbin Boiler supplied steam boiler for the Yiyang Power Plant (Yiyang Power Plant Phase I).
Harbin Boiler supplied steam boiler for the Yiyang Power Plant (Yiyang Power Plant Phase II).
For more details on Yiyang Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.