Presidente Juarez Combined Cycle Power Plant is a 773MW gas fired power project. It is located in Baja California, Mexico. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in July 2001.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 773 773 Active Baja California, Mexico

Description

The project is currently owned by Comision Federal de Electricidad with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Transportadora de Gas Natural de Baja California.

The project generated 5,267,000MWh of electricity.

Presidente Juarez Combined Cycle Power Plant (Presidente Juarez CCGT Power Plant Phase I) consists of 2 steam turbines.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Development Status

The project got commissioned in July 2001.

Power Purchase Agreement

The power generated from the project is sold to Comision Federal de Electricidad under a power purchase agreement with a contracted capacity is 773MW.

Contractors Involved

Grupo Isolux Corsan was selected to render EPC services for the Presidente Juarez Combined Cycle Power Plant (Presidente Juarez CCGT Power Plant Phase II).

Presidente Juarez Combined Cycle Power Plant (Presidente Juarez CCGT Power Plant Phase I) is equipped with GE Power gas turbines. The Gas fired phase consists 2 gas turbines.

Presidente Juarez Combined Cycle Power Plant (Presidente Juarez CCGT Power Plant Phase II) is equipped with Siemens SGT6 5000F gas turbine. The phase consists of 1 gas turbine.

Presidente Juarez Combined Cycle Power Plant (Presidente Juarez CCGT Power Plant Phase II) is equipped with Siemens SST-700/900 steam turbine. The phase consists of 1 steam turbine.

GE Power supplied electric generator for the Presidente Juarez Combined Cycle Power Plant (Presidente Juarez CCGT Power Plant Phase I).

Siemens supplied electric generator for the Presidente Juarez Combined Cycle Power Plant (Presidente Juarez CCGT Power Plant Phase II).

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.