Rayonier Fernandina Biomass Power Plant Unit II is a 22MW biopower project. It is located in Florida, the US. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in October 2012.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Biopower 22 22 Active Florida, the US

Description

The project is currently owned by Rayonier Advanced Materials.

The project cost is $65.83m.

Rayonier Fernandina Biomass Power Plant Unit II is a combined heat and power (CHP) project. Wood waste which is a kind of wood by-product is used as a feedstock to power the project.

The project consists of 1 turbine with 22MW nameplate capacity.

Development Status

The project got commissioned in October 2012.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.