Riyadh PP7 Gas Turbine Power Plant is a 1,315.6MW gas fired power project. It is located in Al Riyadh, Saudi Arabia. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 1980.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 1,315.6 1,315.6 Active Al Riyadh, Saudi Arabia

Description

The project is currently owned by Saudi Electricity.

It is a gas turbine power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Diesel.

Development Status

The project got commissioned in 1980.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Contractors Involved

Riyadh PP7 Gas Turbine Power Plant (Riyadh PP7 Gas Turbine Power Plant Phase I) is equipped with GE Power MS7001E gas turbines. The phase consists of 4 gas turbines with 50MW nameplate capacity.

Riyadh PP7 Gas Turbine Power Plant (Riyadh PP7 Gas Turbine Power Plant Phase II) is equipped with GE Power gas turbines. The phase consists of 4 gas turbines, each with 50MW nameplate capacity.

Riyadh PP7 Gas Turbine Power Plant (Riyadh PP7 Gas Turbine Power Plant Phase III) is equipped with GE Power 7E.03 gas turbines. The phase consists of 6 gas turbines with 57.6MW nameplate capacity.

Riyadh PP7 Gas Turbine Power Plant (Riyadh PP7 Gas Turbine Power Plant Phase IV) is equipped with Siemens SGT6-3000E gas turbines. The phase consists of 2 gas turbines with 85MW nameplate capacity.

GE Power supplied 7A3 electric generator for the Riyadh PP7 Gas Turbine Power Plant (Riyadh PP7 Gas Turbine Power Plant Phase I).

GE Power supplied 7A3 electric generator for the Riyadh PP7 Gas Turbine Power Plant (Riyadh PP7 Gas Turbine Power Plant Phase II).

GE Power supplied 7A6 electric generator for the Riyadh PP7 Gas Turbine Power Plant (Riyadh PP7 Gas Turbine Power Plant Phase III).

Siemens supplied TLRI 100/30-36 electric generator for the Riyadh PP7 Gas Turbine Power Plant (Riyadh PP7 Gas Turbine Power Plant Phase IV).

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.