Ryazanskaya GRES Phase II is a 1,600MW gas fired power project. It is located in Ryazan, Russia. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 1980.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 1,600 | 1,600 | – | Active | Ryazan, Russia |
---|
Description
The project is currently owned by OGK-2 with a stake of 100%.
It is a steam turbine with cogen power plant that is used for Baseload. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Fuel Oil.
Development Status
The project got commissioned in December 1980.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataContractors Involved
Leningradsky Metallichesky Zavod was selected as the turbine supplier for thermal power project. The project consists of 2 units of K-800-240 turbines, each with 800MW nameplate capacity.
Electrosila supplied TZV-800-2UZ electric generator for the Ryazanskaya GRES Phase II (Ryazanskaya GRES Phase II Unit I).
Electrosila supplied TZV-800-2UZ electric generator for the Ryazanskaya GRES Phase II (Ryazanskaya GRES Phase II Unit II).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Ryazanskaya GRES Phase II (Ryazanskaya GRES Phase II Unit I).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Ryazanskaya GRES Phase II (Ryazanskaya GRES Phase II Unit II).
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.