San Isidro Combined Cycle Power Plant is a 732MW gas fired power project. It is located in Valparaiso, Chile. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 1998.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 732 | 732 | – | Active | Valparaiso, Chile |
---|
Description
The project is currently owned by Enel Generacion Chile with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Diesel.
Development Status
The project got commissioned in 1998.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataPower Purchase Agreement
The power generated from the project is sold to Sistema Interconectado Central under a power purchase agreement.
Contractors Involved
San Isidro Combined Cycle Power Plant (San Isidro CCGT Power Plant Block I) is equipped with Mitsubishi Power M701F gas turbine. The phase consists of 1 gas turbine with 240MW nameplate capacity.
San Isidro Combined Cycle Power Plant (San Isidro CCGT Power Plant Block I) is equipped with Mitsubishi Power SRT-40.5AX steam turbine. The phase consists of 1 steam turbine with 139MW nameplate capacity.
San Isidro Combined Cycle Power Plant (San Isidro CCGT Power Plant Block II) is equipped with Mitsubishi Power M701F gas turbine. The phase consists of 1 gas turbine with 248.29MW nameplate capacity.
San Isidro Combined Cycle Power Plant (San Isidro CCGT Power Plant Block II) is equipped with Mitsubishi Power SRT-40.5AX steam turbine. The phase consists of 1 steam turbine with 104.71MW nameplate capacity.
Mitsubishi Power supplied 3-Phase electric generator for the San Isidro Combined Cycle Power Plant (San Isidro CCGT Power Plant Block I).
Mitsubishi Power supplied 3-Phase Protected electric generator for the San Isidro Combined Cycle Power Plant (San Isidro CCGT Power Plant Block II).
Mitsubishi Power supplied steam boiler for the San Isidro Combined Cycle Power Plant (San Isidro CCGT Power Plant Block I).
Mitsubishi Power supplied steam boiler for the San Isidro Combined Cycle Power Plant (San Isidro CCGT Power Plant Block II).
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.