Sanandaj Combined Cycle Power Plant is a 956MW gas fired power project. It is located in Kurdistan, Iran. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in November 2005.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 956 | 956 | – | Active | Kurdistan, Iran |
---|
Description
The project is currently owned by MAPNA Group.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Gas Oil.
The project cost is $40m.
Development Status
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataThe project got commissioned in November 2005.
Contractors Involved
MAPNA Combined Cycle Power plants Constraction & Development was selected to render EPC services for the gas fired power project.
Sanandaj Combined Cycle Power Plant (Sanandaj Combined Cycle Power Plant Block I Unit I) is equipped with MAPNA Turbine Engineering & Manufacturing MGT-70 gas turbine. The phase consists of 1 gas turbine with 159MW nameplate capacity.
Sanandaj Combined Cycle Power Plant (Sanandaj Combined Cycle Power Plant Block I Unit II) is equipped with MAPNA Turbine Engineering & Manufacturing MGT-70 gas turbine. The phase consists of 1 gas turbine with 159MW nameplate capacity.
Sanandaj Combined Cycle Power Plant (Sanandaj Combined Cycle Power Plant Block I Unit III) is equipped with Siemens E30-16-1×6.3 steam turbine. The phase consists of 1 steam turbine with 160MW nameplate capacity.
Sanandaj Combined Cycle Power Plant (Sanandaj Combined Cycle Power Plant Block II Unit I) is equipped with MAPNA Turbine Engineering & Manufacturing MGT-70 gas turbine. The phase consists of 1 gas turbine with 159MW nameplate capacity.
Sanandaj Combined Cycle Power Plant (Sanandaj Combined Cycle Power Plant Block II Unit II) is equipped with MAPNA Turbine Engineering & Manufacturing MGT-70 gas turbine. The phase consists of 1 gas turbine with 159MW nameplate capacity.
Sanandaj Combined Cycle Power Plant (Sanandaj Combined Cycle Power Plant Block II Unit III) is equipped with Siemens E30-16-1×6.3 steam turbine. The phase consists of 1 steam turbine with 160MW nameplate capacity.
MAPNA Generator Engineering & Manufacturing supplied electric generator for the project.
GE Power supplied steam boiler for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.