Shandong Zhanhua Binzhou Shenhua Wind Power Plant is a 99MW onshore wind power project. It is located in Shandong, China. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in October 2009.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Onshore | 99 | 99 | – | Active | Shandong, China |
---|
Description
Shenhua Renewable and CLP Holdings are currently owning the project having ownership stake of 51% and 49% respectively.
The Shandong Zhanhua Binzhou Shenhua Wind Power Plant (Shandong Zhanhua Binzhou Shenhua Wind Power Plant- Phase IA), has 80m high towers.
The Shandong Zhanhua Binzhou Shenhua Wind Power Plant (Shandong Zhanhua Binzhou Shenhua Wind Power Plant- Phase IB), has 80m high towers.
The Shandong Zhanhua Binzhou Shenhua Wind Power Plant (Shandong Zhanhua Binzhou Shenhua Wind Power Plant- Phase II), has 70m high towers.

US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataDevelopment Status
The project is currently active. The project got commissioned in October 2009.
Power Purchase Agreement
North China Power Grid is the power offtaker from the project.
Contractors Involved
Shandong Zhanhua Binzhou Shenhua Wind Power Plant (Shandong Zhanhua Binzhou Shenhua Wind Power Plant- Phase IA) is equipped with Senvion turbines. The phase consists of 24 turbines, each with 2MW nameplate capacity.
Shandong Zhanhua Binzhou Shenhua Wind Power Plant (Shandong Zhanhua Binzhou Shenhua Wind Power Plant- Phase IB) is equipped with Senvion turbine. The phase consists of 1 turbine with 1.5MW nameplate capacity.
Shandong Zhanhua Binzhou Shenhua Wind Power Plant (Shandong Zhanhua Binzhou Shenhua Wind Power Plant- Phase II) is equipped with Xinjiang Goldwind Science & Technology turbines. The phase consists of 33 turbines, each with 1.5MW nameplate capacity.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.