Sherwood H Smith Jr Gas Turbine Power Plant is a 997MW gas fired power project. It is located in North Carolina, the US. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in May 2001.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 997 997 Active North Carolina, the US

Description

The project is currently owned by Duke Energy Progress with a stake of 100%.

It is a Gas Turbine power plant that is used for Peakload. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Distillate Fuel Oil. The fuel is procured from Piedmont Natural Gas Pipeline.

The project generated 3,073,958MWh of electricity.

Sherwood H Smith Jr Gas Turbine Power Plant (Sherwood H Smith Jr Gas Turbine Power Plant Unit V) consists of 1 gas turbine with 199.4MW nameplate capacity.

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

Development Status

The project got commissioned in May 2001.

Contractors Involved

Gemma Power Systems was selected to render EPC services for the gas fired power project.

Sherwood H Smith Jr Gas Turbine Power Plant (Sherwood H Smith Jr Gas Turbine Power Plant Unit I) is equipped with GE Power 7FA gas turbine. The phase consists of 1 gas turbine with 199.4MW nameplate capacity.

Sherwood H Smith Jr Gas Turbine Power Plant (Sherwood H Smith Jr Gas Turbine Power Plant Unit II) is equipped with GE Power 7FA gas turbine. The phase consists of 1 gas turbine with 199.4MW nameplate capacity.

Sherwood H Smith Jr Gas Turbine Power Plant (Sherwood H Smith Jr Gas Turbine Power Plant Unit III) is equipped with GE Power 7FA gas turbine. The phase consists of 1 gas turbine with 199.4MW nameplate capacity.

Sherwood H Smith Jr Gas Turbine Power Plant (Sherwood H Smith Jr Gas Turbine Power Plant Unit IV) is equipped with GE Power 7FA gas turbine. The phase consists of 1 gas turbine with 199.4MW nameplate capacity.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.