Silver Queen Wind Farm is a 303MW onshore wind power project. It is planned in Iowa, the US. The project is currently in permitting stage. It will be developed in multiple phases. Post completion of the construction, the project is expected to get commissioned in 2024.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Onshore | 303 | – | 303 | Permitting | Iowa, the US | Scout Clean Energy |
---|
Description
The project is being developed and currently owned by Scout Clean Energy.
The electricitiy generated from the plant will offset 816,466t of carbon dioxide emissions (CO2) a year.
Development Status
Post completion of the construction, the project is expected to get commissioned in 2024.
Contractors Involved
Silver Queen Wind Farm (Silver Queen Wind Farm – Phase I) will be equipped with GE Renewable Energy turbines. The phase consists of 50 turbines, each with 3.03MW nameplate capacity.
Silver Queen Wind Farm (Silver Queen Wind Farm – Phase II) will be equipped with GE Renewable Energy turbines. The phase consists of 50 turbines, each with 3.03MW nameplate capacity.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.