Sir Adam Beck 1 is a 450MW hydro power project. It is located on Niagara river/basin in Ontario, Canada. The project is currently active. It has been developed in single phase. The project construction commenced in 1917 and subsequently entered into commercial operation in 1922.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 450 450 Active Ontario, Canada Hydro-Electric Power Commission of Ontario

Description

The project was developed by Hydro-Electric Power Commission of Ontario and is currently owned by Ontario Power Generation with a stake of 100%.

The net head of the project is 91.4m. The total number of penstocks, pipes or long channels that carry water down from the hydroelectric reservoir to the turbines inside the actual power station, are 10 in number. The penstock length is 116.7m. The penstock diameter is 4.9m. Sir Adam Beck 1 underwent through rehabilitation & modernization during 2011.

The hydro power project consists of 4 turbines.

Development Status

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

The project construction commenced in 1917 and subsequently entered into commercial operation in 1922.

Contractors Involved

Andritz Hydro was selected as the turbine supplier for the hydro power project. The company provided 2 units of francis turbines.

Andritz Hydro was selected as the turbine supplier for the hydro power project. The company provided 3 units of francis turbines, each with 50MW nameplate capacity.

The electric generators for the project were procured from Andritz Hydro and Voith Hydro Holding.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.