Sohna Road Substation is a 400/220kV substation located in Sohna Road,Gurgaon, Haryana, India. The construction works on Sohna Road Substation began in 2019. The project was commissioned in 2020.
Description
The Sohna Road Substation project is a new substation being operated by Sterlite Grid.
The designed voltage level of the project is 400/220kV, while the operating voltage level is 400/220kV. The step-in voltage of the substation is 400kV and the step-out voltage is 220kV. The substation capacity is 1,000MVA.
Sohna Road Substation has received approval from Haryana Electricity Regulatory Commission to undertake the works on the project.
Contractors involved

US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataGE T&D India was appointed by Sterlite Grid to undertake design and construction works of the Sohna Road Substation.
Methodology
All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.