SolarArise Kheda Solar PV Park is a 75MW solar PV power project. It is located in Uttar Pradesh, India. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in January 2021.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Solar PV | 75 | 75 | – | Active | Uttar Pradesh, India | SolarArise India Projects |
---|
Description
The project is developed and owned by SolarArise India Projects.
SolarArise Kheda Solar PV Park is a ground-mounted solar project.
The project generates 12,000MWh electricity thereby offsetting 45,982t of carbon dioxide emissions (CO2) a year. The project cost is $52.35m.
Development Status
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataThe project got commissioned in January 2021.
Power Purchase Agreement
The power generated from the project is sold to Uttar Pradesh Power under a power purchase agreement. The power is sold at the rate of $0.05kWh for a period of 25 years. The contracted capacity is 75MW.
Contractors Involved
Jakson was selected to render EPC services for the solar PV power project.
JA Solar Holdings was selected as the supplier of the PV modules for the project. The company provided 192,000 modules each with 390W of nameplate capacity.
The inverters were procured from Sungrow Power Supply for the project.
About SolarArise India Projects
SolarArise India Projects Pvt., Ltd. is an owner and operator of solar plants.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.