There were 31 T&D project tenders announced in the South and Central America region in Q1 2021, marking a rise of 107% over the last four-quarter average of 15, according to GlobalData’s power industry tenders database.
- Embed this chart
Embed this chart into your website
Copy and paste the code below into your website to display the chart.
T&D Project stood at first place when compared with other power tender categories in the South and Central America region in Q1 2021 with 31 tenders and a 34.1% share, followed by T&D Equipment with 27 tenders and a 29.7% share and Power Plant with 27 tenders and a 29.7% share during the quarter.
The proportion of tenders by category tracked by GlobalData in the quarter was as follows:
- Project Implementation: 26 tenders and an 83.9% share
- Consulting & Similar Services: three tenders and a 9.7% share
- Repair, Maintenance, Upgrade & Others: two tenders and a 6.5% share.
Solar is top technology for South and Central America T&D project tenders in Q1 2021
Looking at T&D project tenders by the type of technology in the South and Central America region, solar accounted for seven tenders with an 87.5% share, followed by geothermal with one tender and a 12.5% share.
- Embed this chart
Embed this chart into your website
Copy and paste the code below into your website to display the chart.
South and Central America T&D project tenders in Q1 2021: Top issuers by capacity
The top issuer of T&D project tenders for the quarter in terms of power capacity involved in South and Central America was:Guyana Energy Agency (Guyana) with 1.03MW from seven tenders.
All publicly-announced tenders are included in this analysis drawn from GlobalData’s Power database, which covers power plants, T&D projects, equipment markets, analysis reports, capacity and generation, and tracks tenders and contracts on a real-time basis.